Completed works:

  • The kerbing and paving is complete on the North West corner of the War Memorial roundabout.
  • Paving has continued outside Prezzo and across the Kelsey Square / High Street junction and outside Haks barbers. The cross over entrance to Coopers Mews has been completed.
  • Kerb laying and new drainage has been completed between Burrell Row and Sainsbury.

Phase 5 works Lidl to Village Way:

  • From Monday, July 21, the junction between Burnhill Road and Kelsey Square has been closed to traffic. The road will be re-open the week starting Monday, August 6 and all traffic management will revert to normal except for left turns out of Kelsey Square on to the High Street.
  • The junction of Kelsey Square and Burnhill Road will be jet washed and due open to pedestrians next week.
  • Paving will be completed outside Zizis.
  • The parking bays outside Zizzi will be retained for deliveries only.
    .

War Memorial Roundabout:

  • Preparation for groundworks will commence on the North-East corner of the War Memorial roundabout outside the cinema.
  • Street lights will continue to be installed at various locations.
  • Cycle stands to be installed at various locations.

Burrell Row to Village Way:

  • Kerbing and paving will continue.